The Enguri 1’300 MW hydropower plant, equipped with 5 vertical Francis units under a gross head of maximum 410 m was entirely rehabilitated.
Apart from the production units (new water-cooled generator stator windings, stator core, re-isolation, cooler and digital and hydraulic governors), the rehabilitation works included a new drainage pumping system; firefighting system; battery room; transformers control system; excitation system; inlet valve control systems, medium and low voltage switchgear, battery and compressed air.
 

Services

Procurement and construction management