You are here

15.09.2015

Flood control and renaturalization measures for Rivers Kleine Emme and Reuss, Buchrain

An engineering consortium comprising Gruner Berchtold Eicher AG, Staubli, Kurath Partner AG, Aquarius and various other sub-designers was commissioned by paper manufacturer Perlen Papier AG to provide services in connection with the renewal of a concession for two hydropower plants together with flood control measures for the Rivers Kleine Emme and Reuss.

Gruner Berchtold Eicher AG is responsible for the overall project management and design of the works on the left bank of the River Reuss (flood corridor, weir access road, upstream fish pass).

The project embraces:
- Services in connection with renewal of concession for two hydropower plants, with a capacity of 2 MW, owned by Perlen Papier AG
- Flood control measures
- Design of fish passage facilities (upstream and downstream fish passes, specification of residual flow)
- Eco-friendly improvements
 

23.09.2015

Tunnels du Golden Pass - Inspection principale

La société Golden Pass a mandaté Stucky SA pour effectuer les inspections principales sur 24 tunnels des lignes du MOB (Montreux Oberland Bernois) et du MVR (Montreux Vevey Région). Ces inspections se déroulent tous les 6 ans. Elles permettent à l’exploitant de connaître l’état de ses ouvrages (pour la plupart mis en service au début du 20ème siècle) et ainsi de planifier les interventions d’assainissement. Durant toutes les nuits du mois d’octobre de cette année, environ 6 km de tunnels seront inspectés par Stucky entre Montreux et Zweisimmen.

Login

15.09.2015

Hochwasser-schutz und Renaturierung Kleine Emme und Reuss, Buchrain

Die Ingenieurgemeinschaft bestehend aus Gruner Berchtold Eicher AG, Staubli, Kurath Partner AG, Aquarius sowie diversen anderen Subplanern wurde von der Perlen Papier AG mit einer Konzessionserneuerung von zwei Kraftwerken und dem Hochwasserschutz der Kleinen Emme und Reuss beauftragt.

Gruner Berchtold Eicher AG ist verantwortlich für die Gesamtprojektleitung sowie die Projektierung der linken Reussuferseite (Flutkorridor, Zufahrt Wehr, Fischaufstieg).

Das Projekt umfasst:

- die Konzessionserneuerung für zwei Kraftwerke der Perlen Papier AG mit einer Leistung von 2 MW

- die Sicherstellung des Hochwasserschutzes

- die Projektierung von Massnahmen für die Gewährleistung der Fischgängigkeit (Fischauf- und ab-stieg, Festlegung der Dotierwassermenge)

- ökologische Aufwertungen

Tech­nique du bâtiment

Roche Tower, Bâle

Des approches innovantes associées à une conception modulaire cohérente et une réalisation industrielle caractérisent le processus de planification de ce bâtiment high-tech destiné à devenir le plus haut gratteciel de Suisse, la Roche Tower à Bâle.

Prestations
Alimentation électrique, dispositif de protection contre la foudre, installations électriques, infrastructure informatique, éclairage Minergie, systèmes de sécurité, technologie audio/vidéo et automatisation du bâtiment.

Gruner SA s’est vu confier le mandat de prestations d’ingénierie en géotechnique et excavation.

Contact

 
Gruner Kiwi AG
Im Schörli 5
8600 Dübendorf
Switzerland
Contact Person
Michael Reuteler
T +41 44 802 11 97
obfuscationXfuncMichael.Reuteler@grobfuscationXfuncuner.ch
Michael Reuteler Gruner Gruneko AG

Building services

Roche Tower, Basel

Innovative methods with unified modular design and industrial-scale production typify the planning process behind this high-tech construction, set to be the tallest high-rise building in Switzerland, the Roche Tower in Basel.

Services
Power supply, lightning protection system, electrical and other installations, IT infrastructure, Minergie lighting, safety and security systems, audio/video technology and building automation.

Gruner Ltd has been commissioned to conduct engineering services including geotechnical engineering and excavation.

Contact

 
Gruner Kiwi AG
Im Schörli 5
8600 Dübendorf
Switzerland
Contact Person
Michael Reuteler
T +41 44 802 11 97
obfuscationXfuncMichael.Reuteler@grobfuscationXfuncuner.ch
Michael Reuteler Gruner Gruneko AG

Gebäudetechnik

Roche Tower, Basel

Innovative Ansätze mit einer durchgängigen modularen Planung und industriellen Fertigung prägen den Planungsprozess dieses Hightech-Gebäudes: das derzeit höchste Hochhaus der Schweiz, der Roche Tower in Basel.

Leistungen
Stromversorgung, Blitzschutzanlage, Elektroanlagen und Installationen, IT-Infrastruktur, Minergie-Beleuchtung, Safety- und Security-Systeme, Audio-/Video-Technik und Gebäudeautomation.

Gruner wurde zusätzlich für die Ingenieurleistungen für Geotechnik und Baugrube beauftragt.

Contact

 
Gruner Gruneko AG
Im Schörli 5
8600 Dübendorf
Switzerland
Contact Person
Michael Reuteler
T +41 44 802 11 97
obfuscationXfuncMichael.Reuteler@grobfuscationXfuncuner.ch
Michael Reuteler Gruner Gruneko AG

19.08.2015

Mandat géotechnique et excavation pour le projet Roche

La société F. Hoffmann-La Roche SA agrandit et rénove l’infrastructure des bâtiments sur son site bâlois, et fait construire un nouveau centre de recherche et développement au cours de la prochaine décennie. Les deux tours appelées Bâtiment 1 et Bâtiment 2 ainsi qu’un total de huit nouveaux bâtiments de bureaux et de laboratoires qui remplaceront les anciens bâtiments du site industriel actuel, visent à permettre un regroupement des postes de travail sur un seul site.

Gruner SA s’est vu confier le mandat de prestations d’ingénierie en géotechnique et excavation pour les bâtiments 8 et 11 conçus par le bureau d’architectes Herzog & de Meuron. Il sera nécessaire de procéder à une excavation à soutènement multiple de 22 à 26 mètres de profondeur, d’une surface d’environ 4000 m2 pour pouvoir construire le sous-sol situé au niveau de la nappe phréatique.
 

19.08.2015

Geo­tech­nical engi­neer­ing and excavation contract for Roche project

F. Hofmann-La Roche Ltd is extending and renovating the building infrastructure at its existing Basel site and will be realizing a new research and development center in the next ten years. The two high-rises—Building 1 and Building 2—plus a total of eight other new office and laboratory buildings which will replace the older structures on the existing industrial site, should enable the company to concentrate its employees at a single location.

Gruner Ltd has been commissioned to conduct engineering services including geotechnical engineering and excavation for Buildings 8 and 11, which have been designed by architects Herzog & de Meuron. The basement level, which will extend below the water table, will require excavations between 22 and 26 meters deep, braced at several points, with a floor area of approximately 4,000 m2.
 

19.08.2015

Auftrag Geotechnik und Baugrube für Roche Projekt

Die Firma F. Hoffmann-La Roche AG erweitert und erneuert am bestehenden Standort in Basel die Gebäudeinfrastruktur und realisiert in den nächsten zehn Jahren ein neues Forschungs- und Entwicklungszentrum. Die beiden Hochhäuser Bau 1 und Bau 2 sowie insgesamt weitere acht neue Büro- Laborgebäude, welche die ältere Gebäudesubstanz auf dem bestehenden Industrieareal ersetzen, sollen eine Konzentration der Arbeitsplätze an einem Standort ermöglichen.

Die Gruner AG wurde mit dem Auftrag für die Ingenieurleistungen Geotechnik und Baugrube für die vom Architekturbüro Herzog & de Meuron entworfenen Gebäude Bau 8 und 11 betraut. Für das Erstellen des im Grundwasser liegenden Untergeschosses wird eine 22 bis 26 m tiefe, mehrfach verankerte Baugrube mit einer Grundfläche von ca. 4000 m2 notwendig sein.

Pages

Subscribe to Gruner AG RSS