SRES Partial deconstruction WRO
Gutting, demolition of mineral structures, filling of excavation pits
The redevelopment of the Rosental site as part of the SRES project in Basel requires the demolition of the existing buildings 1018 and 1020 and the partial demolition of buildings 1002 and 1013.
Services:
> Coordination of the suspension of media and energies
> Project planning and realization of the remediation of building pollutants
> Project planning and realization of the orderly deconstruction activities
> Design and realization of the retrofitting measures for the remaining parts of the building parts of the building
> Design and realization of the backfilling of the excavation pits